Marine support by HR Wallingford has ranged from definition of shipping and tankage requirements to provision of a dredging observer to oversee GLNG’s portion of dredging and disposal, approximately 22Mm3 of material. HR Wallingford provided wide ranging support in relation to the marine facilities. This included:
HR Wallingford has been retained by GLNG as marine advisor since first involvement on the project in 2008 through pre-FEED, FEED and EPC phases. This demonstrates the value provided by HR Wallingford in supporting successful delivery of this large and complex project.
With the support of HR Wallingford in design and on site guidance, the dredging works for GLNG have been completed within time frame and budget. This is a significant achievement for a dredging project of this scale.
Adam Barber, OSBL Superintendent, Plant and Port